ICIS Long-Term Power: Greek market reform proposal outlines lignite phase-out and capacity market from 2024
Roy Manuell
23-Aug-2021
This story has originally been published for ICIS Long-Term Power Analytics subscribers on 12 August.
Our ICIS Long-Term Power Analytics customers have access to extensive modelling of different options and proposals. Our long-term price forecast now extends out to 2050. If you have not yet subscribed to our products, please get in contact with Justin Banrey (Justin.Banrey@icis.com) or Audrius Sveikys (Audrius.Sveikys@icis.com).
Proposed Greek market reform plans outline a move to a capacity market in 2024 as well as a possible early phase-out of lignite capacity in the same year with the final remaining plant converted to a 1GW CCGT.
While many details are yet to be confirmed, we expect that a capacity market would significantly boost the prospects that a 3.3GW pipeline of proposed gas plants will obtain a grid connection – four plants are currently waiting to make an investment decision – as well as existing assets continue to operate.
Given the expected market tightness in Greece following the lignite phase-out in the early-to-mid 2020s and prior to strong renewable growth, the market reform proposals heavily point to an emphasis on gas to secure Greek supply in this period.
The market reform plan – key points
- Greece plans to introduce a capacity
remuneration mechanism (CRM) from the end of
2023 to incentivise investments in new
gas-fired capacity and storage
- In the interim, the country is planning to invite lignite plants to be part of a strategic reserve between 2021-2023
- Utility PPC may fast track the closure of
the new 660MW Ptolemaida V lignite plant due
online in 2023 with a possible conversion to a
1GW CCGT by 2025
- According to previous plans the under-construction lignite plant will close in 2028 after just five years of operation
- Under the market reform plans, Greece would phase out lignite four years early
- More broadly, PPC has asked to close
lignite capacity prematurely due to
significantly weaker economic conditions for
generation
- The threat of losing so much baseload capacity even earlier has prompted the strategic reserve proposal to ensure security of supply pre-2023
- All currently installed lignite capacity is due to close by 2023 under current PPC proposed plans outlined earlier this year
- There is currently only one confirmed
private gas-fired project – the 825MW CCGT at
by Mytilineos Group at Agios Nikolaos – which
is expected to start commercial operation at
the at the start of 2023
- Four other CCGT projects totalling 3.3GW are relatively far down the permit and licensing process but none of them have reached firm investment decision
- Some small hydro expansion is also planned with an additional 29MW in 2025 and 160MW in 2027
- The proposals also outlined suggested
reforms to the structure of the futures,
day-ahead and intra-day markets to boost
liquidity and competition, as well as a
restructuring to accommodate for both the CRM
and an expected increase in PPAs
- These included lifting of the 20% cap on physical contracts
- A revision of the balancing market in relation to the energy-only market
- The launch of regional intra-day auctions
- Another key feature of the reform plans was
the participation of Demand Side Response (DSR)
and storage systems in the wholesale market as
well as incentivising their participation in a
future CRM
- This includes their introduction to the balancing market from 2022
- Various interconnectors were confirmed including one external with Bulgaria from 2023 and many internal to connect the many Greek islands
- We will wait for a conformation of these
plans prior to a major adjustment to any of our
assumptions
- That said, we will make some amendments to our gas capacity and power plant database at the end of September based on some new details in the proposals and recent clarity from investor releases
Analysis
Lignite phase-out
- State utility PPC had planned to start
closing existing lignite plants from 2021 with
all currently-installed assets to leave the
grid by the end of 2023
- This has been driven by a steady deterioration in the profitability of lignite-fired generation due to bullish carbon prices, as well as easing gas markets in 2019 and 2020, that has led to a continental fuel switch to gas
- In 2014, lignite plants covered 50% of Greek generation. This share has shrunk to 11% in 2020 and is expected to drop to 8% in 2021 due to extremely high carbon costs pushing lignite out of the merit order, according to data by grid operator IPTO
Our Base Case forecasts anticipate a sharp reduction from 11% in 2021 to less than 2% in 2024 due to both capacity closures and bullish carbon price expectations
- Modelling commissioned for the market reform proposal demonstrated the heavy losses inflicted on lignite generation in the period November 2020 to April 2021 – (see Table 12 in the proposal document)
-
-
- At the same time, the Greek TSO IPTO has stated that Greece will face a significant capacity shortfall if lignite plants were to retire before the new plants are built
- This is the reasoning for transferring outgoing lignite capacity to a reserve – and a similar process has been the case in Germany over the past few years
- In the German case this translates into an annual payment per MW as well as prices per kWh generated on top of this
- Transferring loss-making assets into a reserve can be costly but also reflects the gravity of the perceived low security of supply
-
- We applied de-rating factors to our current
Base Case Greek capacity assumptions based on
those used in the UK capacity market to
illustrate the shortfall relative to 2021
levels
- Overall, due to hydropower and gas expansion and most lignite units closing in 2023 and 2024, Greece sees an increase in de-rated capacity in 2022 and therefore its supply is not as tight as anticipated
- However, the calculations demonstrate that in the 2024 to 2026 period in particular, supply stands to be significantly tighter than in 2021
- We do not currently assume that all the new CCGT plants are brought online
- One form of flexibility that we see Greece
utilising at present, however, is from Bulgaria
via imports as the new cable between the two
countries comes online in 2023 with imports
jumping in particular in 2025 and 2026
- Overall, the high level of imports between 2024 and 2030 underlines Greek supply tightness in the period following the lignite closures
Capacity market
- As mentioned above, while the weakness of lignite profitability has driven the desire to retire assets but then create a reserve to ensure security of supply, the weakness of gas-fired profitability has equally underlined the drive to opt for a capacity market thereafter
- This has been a trend seen across Europe
with France, Italy, Ireland and Spain adopting
a move to a CRM with many following an earlier
UK model
- In most cases, this has been to ensure that existing CCGTs are incentivised to remain in operation as markets move from coal to gas in the 2020s with some looking for gas capacity expansion on top of this as an option
- Another benefit is that a CRM also offers a potential additional revenue stream for newer emerging technologies such as batteries as is suggested in the Greek reform proposal
- In the case of Greece, as suggested by the
draft, gas-fired capacity made a loss on a MWh
basis in the period November 2020 to April 2021
taking all total costs into account including
CAPEX
- Looking at our own capture price forecasts in relation to the draft’s stated cost per MWh, we do not envisage gas capture prices in Greece reaching anywhere near the level required to meet all costs over the next decade
- The cost per MWh stated in the draft that only includes OPEX and fuel costs also remains very close to, or at parity with, our capture price forecast
- One caveat to add to this is that the draft’s profitability modelling only provided data over a period that saw substantial fluctuations in gas and carbon prices and are not a truly fair comparison to our forecasts
- The results nevertheless calls into question the profitability over the next decade of both a new and existing CCGT in Greece without a capacity market in place to provide additional support
Gas expansion
- The move to fully replace lignite with gas
via a CRM incentive therefore underlines the
Greek ambition to replace coal with gas on a
relatively fast timeline given its previous
reliance on lignite
- Of the future CCGT projects mentioned in the proposals that are additional to the aforementioned 825MW Mytilineos asset – four CCGTs totalling 3.3GW – all are above 650MW and many have now had licences approved but are waiting to make a final investment decision
- Furthermore, several of the planned plants have also successfully applied to increase their prospective capacities to above 800MW from around 600MW
- This suggests the increasing momentum in Greece behind CCGT capacity growth
- Assuming the proposals are confirmed and a CRM structure is decided upon, it is likely that the investment decision to build these future CCGT will be fast-tracked and Greece can therefore expect strong gas capacity expansion in the mid-2020s
- This is the period when we expect de-rated supply to be at its tightest
Next steps
- The new capacity adequacy report by the Greek TSO, which is close to completion, will be submitted and then the European Commission will issue an assessment of the Market Reform Plan
- The Greek Energy Regulator RAE stated that it was optimistic of broad EU acceptance for the proposal describing it as “comprehensive”
Market impact
- Bearish in the event of more than 4GW gas
capacity expansion in the 2023-2025 period plus
the proposed conversion of the new lignite
plant in 2025
- This will ease Greek supply tightness and import reliance in the 2020s
- We will produce some modelling over the coming weeks to measure the impact of a potential 2024 lignite phase-out and the subsequent full gas build
Global News + ICIS Chemical Business (ICB)
See the full picture, with unlimited access to ICIS chemicals news across all markets and regions, plus ICB, the industry-leading magazine for the chemicals industry.
Contact us
Partnering with ICIS unlocks a vision of a future you can trust and achieve. We leverage our unrivalled network of industry experts to deliver a comprehensive market view based on independent and reliable data, insight and analytics.
Contact us to learn how we can support you as you transact today and plan for tomorrow.